When choosing the main material for decoration, will you be worried about the omission of some decoration materials affecting the construction period, or buying too early? There is a close relationship between the order of the main materials and the construction, and sometimes the owner orders the main materials too late or sent Inappropriate delivery time often results in the main material being not supplied in time or in the main material, and may not be temporarily used or stored. That is, it is inconvenient for the construction party and the main material side, and it is more of a chaotic situation. What should you pay attention to when preparing the main material? What is the purchase order of home improvement main materials ? With reference to some of the owner's decoration experience and expert advice, help us to sort out the following order of the main materials to buy home , I hope everyone can learn from some experience.
Home improvement main material preparation work
1. Estimated renovation period
The entire renovation process needs to go through several types of work: carpentry, electricians, hydraulics, tile workers, oil workers, etc. These types of work have a certain order, to eliminate the impact of weather on the construction, a basic home renovation of the basic project usually takes 45 to 60 days. Some main materials, such as wooden doors and cabinets, generally take about 40 days to prepare the goods. This way, it takes at least 85 days from the start of renovation to satisfying the home environment to be able to stay. With ventilation for one month, it takes approximately 115 days.
If you follow the decoration process of construction, stock preparation, and ventilation, I am afraid that there will be an embarrassing situation that “it will not be able to work.†However, if all kinds of work are carried out, the duration will be shortened, and at least one month can be saved. Therefore, before the renovation starts, the owner should use the style of home decoration as the standard and give priority to the purchase of the main material. This will not waste time waiting for the delivery of the main material.
2, reasonable arrangements for the main material order time
There is a close relationship between the order of the main materials and the construction. Sometimes, due to the lateness of the owner’s purchase of the main materials or the improper delivery time, the main material supply may not be timely or the main material may come. However, it may not be used temporarily and there is no storage at all. Construction caused inconvenience, but also made him chaotic. Therefore, Jiuzheng.com reminds the owners that they must make sufficient preparations before the renovation starts, especially on the main materials.
Before the renovation starts, the main materials to be determined include floor heating, cabinets, and heating. In the middle of the renovation, the main materials that can be purchased in parallel with the construction include ceramic tiles, sanitary ware, flooring, doors, custom furniture, and some long-customized materials. It must be a good time. Do not give up because of the lack of materials after the start of work. And other soft decorations can be slowly selected in combination with the overall style.
3, è¶ ä¹° ä¹° ä¹° ä¹° ä¹° ä¹° more affordable
In general, the promotion of the building materials market has its own “timetableâ€. On major holidays or large-scale events, prices will be more favorable. In contrast, some of the usual promotions in the week have profit, but the discount rate cannot be the same. Therefore, from the perspective of saving the budget, in the holiday or large-scale promotional activities, more shopping, watching more, you can first pay the deposit, lock product discounts, but also a good way.
Home improvement main material purchase order
â–²In the pre-construction period (3-5 days), before the water electrician enters the market, the kitchen needs to order cabinets, stoves, hoods, etc.
â–² Toilets need to order sanitary ware, water heaters, toilet bowls, wash bowls, etc.
â–²Hydroelectricians can order wall tiles and floor tiles after the slot is finished.
â–² After the installation of water and electricity, the door can be set up.
â–² Prior to entering the site (3 to 5 days ago), the stone material should be well-prepared.
â–²After the cement enters the field, it is possible to arrange the construction of suspended ceilings, mainly by contacting the professional drilling and opening air conditioning holes and water heater vents.
â–² Before finishing the paint (3 to 5 days ago), wallpaper and partition glass can be ordered.
â–²After scraping painter's wall putty, the main purchase is aluminum buckle plate, bathroom heater, kitchen ceiling lamp exhaust fan. At this time, the kitchen utensils bought earlier can also be pulled into the market.
▲ After the painter finishes the first pass of the primer, it is necessary to inform the installation of the door and the door cover, and at the same time to purchase the door's accessories—locks, hinges and handles.
â–² During the painting of latex paint, wood flooring, lamps, curtains, pendants, sanitary ware, and switch panels need to be booked.
â–² Finally, you can consider the purchase of furniture and the installation of curtains.
Editing summary: The main material is the highlight of the decoration process. The selection time of the main material is directly related to the progress of the decoration, thus affecting the owner's time to stay in the new home. Therefore, in the renovation, it is best to purchase the main material in advance, so as to ensure the smooth connection of the various aspects of the decoration, saving decoration time.
Home Improvement Home Decoration Size Data Home Improvement Home Decoration Home Improvement
Aluminum Door Handle On Iron Rosette
Aluminum Door Handle On Iron Rosette,Brass Lever Door Handle,Iron Rosette Door Handle,Iron Rose Door Handle
Wenzhou Shenghong Metal Products Co.,Ltd , https://www.shenghonglock.com