Due to the material and the beautiful appearance, the steel-wooden door has become a popular interior door choice, but the steel-wood door is more complicated than the ordinary wooden door installation, and there are many precautions. Next, I will give you a detailed introduction to the installation process and precautions for steel doors.
Steel wood door installation process
First, measure the thickness of the wall, the width and height of the door hole, and then measure the length of the top frame of the door frame and the length of the frame to check whether it matches the door hole.
Second, assemble the door frame. The top frame and the frame should be connected at an angle of 90°. On both sides of the frame, 4-6 pieces of connecting piece are used for fixing, and then the locking foot strip and the locking angle strip are nailed. The top frame is placed on the top of the two frames. The inner width of the two frame doors should be 7 mm more than the width of the door leaf. The inner height between the door frame door and the floor should be 13 mm higher than the height of the door leaf.
Third, install the door frame. Put the assembled door frame into the door hole and check whether it is vertical. Use the nail hole of the connecting piece as a point to determine the position of the nail hole on the wall. Then use the nail to fix the connecting piece to the wall, and in the door frame and wall. The gap of the body is embedded in the wooden strip to ensure that the connection between the door frame and the wall is firm and compact.
Fourth, install the door hinge. First screw a screw on the upper and lower hinges, then close the door, check whether the gap is suitable, and whether the door and the door are in the same plane, ensure that the door is not misplaced, the door does not fall, then tighten the other screws, do not screw the screws directly. Inside the box. When installing the door frame and the door leaf, ensure that the door opening is consistent, the door leaf and the door lock are flexible to open and close, the gap around the door leaf is reasonably consistent, the connection gap is firm and tight, and the decorative surface is not damaged.
Fifth, install the lines. It can be determined according to the width of the wall and the door frame. If the wall is narrower than the frame, the wider side of the line can be placed against the wall. If the frame is narrower than the wall, the reverse is true.
Sixth, glue the buckle on the steel door door bar to dry, and then buckle the groove on the entry bar. This is the only place where glue is needed during the entire installation process.
Precautions for acceptance of steel doors
1. Check whether the steel-wood door structure is firm, flat and without warping.
2, steel wood door frame, fan groove should ensure tight fitting, check whether the rubber is cemented, and tighten with rubber wedge. Also check if the steel door frame and the wall are filled.
3. The door frame of the steel-wood door should be straight and the wound should be flat.
4, the steel wood door hardware installation position should be appropriate, the groove side is neat. Steel wood door draping, capping strips, press-strips, and sealing strips should be installed in the same size and securely joined to the steel-wood doors.
Concerned about surprises
Label: Steel wood door installation process and precautions
Previous: Analysis: Is the bamboo floor good or the wooden floor? Next: How to identify the aluminum alloy door and window
Door Stoppers,Under Door Draft Stopper,Door Blocker,Door Wind Stopper
Jiaxing Gates Hardware Products Co.,Ltd , https://www.jxgateshardware.com